1540 N VINE ST 90028
APPLICATION / PERMIT NUMBER: 14043-10000-03863
PLAN CHECK / JOB NUMBER: M14LA04666

Plan Check and Permit Information


GROUP: Mechanical
TYPE: Fire Sprinkler
SUB-TYPE: Commercial
PRIMARY USE: N/A
WORK DESCRIPTION: Installation of fire sprinkler system for 7 Story mixed use building with 4 levels subterranian. Includes standpipes and fire pump.
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 01/14/2015 ISSUING OFFICE: Metro
CURRENT STATUS: Permit Finaled CURRENT STATUS DATE: 06/14/2016

Permit Application Status History
Submitted 09/18/2014 APPLICANT
Assigned to Plan Check Engineer 09/25/2014 MANOUCHEHR SHAHRESTANI
Corrections Issued 09/29/2014 MANOUCHEHR SHAHRESTANI
Quality Review Completed 09/29/2014 DOMENICO BARBATO
Corrections Issued 09/30/2014 MANOUCHEHR SHAHRESTANI
Corrections Issued 10/23/2014 MANOUCHEHR SHAHRESTANI
Corrections Issued 01/08/2015 MANOUCHEHR SHAHRESTANI
Plan Check Approved 01/09/2015 MANOUCHEHR SHAHRESTANI
Issued 01/14/2015 LADBS
Permit Finaled 06/13/2016 TODD JENKINS

Permit Application Clearance Information
Project located in CRA area Cleared 01/14/2015 JIM URQUHART

Licensed Professional/Contractor Information
Contractor Information
Prime Fire Protection; Lic. No.: 963462-C16
1332 ALLEN AVENUE
GLENDALE, CA  91201

Inspection Activity Information

Inspector Information
KEVIN SIMONDS, (213) 202-9887
Office Hours: 7:00-8:00 AM MON-FRI
VICENTE DIAZ, (213) 202-9887
Office Hours: 7:00-8:00 AM MON-FRI
DAVID JOHNSON, (213) 202-9887
Office Hours: 7:00-8:00 AM MON-FRI
JASON WILSON, (213) 202-9887
Office Hours: 7:00-8:00 AM MON-FRI
WILLEM FELDER, (213) 202-9887
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  No data available

Inspection Request History
  Rough   03/23/2015   Partial Inspection   TODD JENKINS
  Standpipe Hydro   03/23/2015   Partial Inspection   TODD JENKINS
  Standpipe Hydro   04/22/2015   Corrections Issued   TODD JENKINS
  Standpipe Hydro   05/04/2015   Partial Approval   TODD JENKINS
  Rough   05/05/2015   Partial Approval   TODD JENKINS
  Rough   05/06/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   05/08/2015   Partial Inspection   TODD JENKINS
  Rough   05/08/2015   Corrections Issued   TODD JENKINS
  Rough   05/14/2015   Corrections Issued   GUADALUPE TOLEDO
  Rough   05/20/2015   Corrections Issued   GUADALUPE TOLEDO
  Overhead Hydro   05/22/2015   Partial Approval   VICENTE DIAZ
  Rough   05/22/2015   Partial Approval   VICENTE DIAZ
  Overhead Hydro   05/27/2015   Partial Approval   TODD JENKINS
  Rough   05/27/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   06/03/2015   Partial Approval   TODD JENKINS
  Rough   06/03/2015   Corrections Issued   TODD JENKINS
  Overhead Hydro   06/04/2015   Partial Approval   TODD JENKINS
  Rough   06/04/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   06/08/2015   Partial Approval   TODD JENKINS
  Rough   06/08/2015   Partial Approval   TODD JENKINS
  Rough   06/09/2015   Partial Approval   TODD JENKINS
  Rough   06/10/2015   Partial Approval   GUADALUPE TOLEDO
  Overhead Hydro   06/11/2015   Partial Approval   TODD JENKINS
  Rough   06/11/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   06/12/2015   Partial Approval   TODD JENKINS
  Rough   06/12/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   06/15/2015   Partial Approval   TODD JENKINS
  Rough   06/15/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   06/16/2015   Partial Approval   TODD JENKINS
  Rough   06/16/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   06/29/2015   Not Ready for Inspection   VICENTE DIAZ
  Rough   06/29/2015   Corrections Issued   VICENTE DIAZ
  Overhead Hydro   06/30/2015   Partial Approval   VICENTE DIAZ
  Rough   06/30/2015   Partial Approval   VICENTE DIAZ
  Overhead Hydro   07/07/2015   Partial Approval   TODD JENKINS
  Rough   07/07/2015   Partial Inspection   TODD JENKINS
  Rough   07/09/2015   Corrections Issued   VICENTE DIAZ
  Overhead Hydro   07/21/2015   Partial Approval   VICENTE DIAZ
  Rough   07/21/2015   Partial Approval   VICENTE DIAZ
  Rough   07/22/2015   Corrections Issued   TODD JENKINS
  Rough   07/29/2015   Partial Approval   VICENTE DIAZ
  Overhead Hydro   08/04/2015   Partial Approval   TODD JENKINS
  Rough   08/04/2015   Partial Approval   TODD JENKINS
  Rough   08/14/2015   Partial Approval   GUADALUPE TOLEDO
  Overhead Hydro   08/17/2015   Partial Approval   VICENTE DIAZ
  Rough   08/17/2015   Partial Approval   VICENTE DIAZ
  Rough   08/24/2015   Corrections Issued   JOSEPH TAYLOR
  Overhead Hydro   08/27/2015   Partial Approval   TODD JENKINS
  Rough   08/27/2015   Partial Approval   TODD JENKINS
  Rough   08/28/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   08/31/2015   Not Ready for Inspection   TODD JENKINS
  Rough   08/31/2015   Corrections Issued   TODD JENKINS
  Overhead Hydro   09/04/2015   Partial Approval   TODD JENKINS
  Rough   09/04/2015   Partial Approval   TODD JENKINS
  Rough   09/09/2015   Partial Approval   JOSEPH TAYLOR
  Overhead Hydro   09/15/2015   Partial Approval   VICENTE DIAZ
  Rough   09/15/2015   Partial Approval   VICENTE DIAZ
  Rough   09/16/2015   Partial Approval   JOSEPH TAYLOR
  Rough   09/18/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   09/22/2015   Partial Approval   TODD JENKINS
  Rough   09/22/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   09/30/2015   Partial Approval   TODD JENKINS
  Rough   09/30/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   10/05/2015   Partial Approval   TODD JENKINS
  Rough   10/05/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   10/07/2015   Partial Approval   TODD JENKINS
  Rough   10/07/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   10/09/2015   Partial Approval   TODD JENKINS
  Rough   10/09/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   10/15/2015   Partial Approval   TODD JENKINS
  Rough   10/15/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   10/26/2015   Partial Approval   TODD JENKINS
  Rough   10/26/2015   Partial Approval   TODD JENKINS
  Underground Flush   10/30/2015   Approved   TODD JENKINS
  Underground Hydro   10/30/2015   Approved   TODD JENKINS
  Underground Hydro   11/02/2015   Approved   TODD JENKINS
  Overhead Hydro   11/05/2015   Partial Approval   TODD JENKINS
  Rough   11/05/2015   Partial Approval   TODD JENKINS
  Rough   11/10/2015   Corrections Issued   TODD JENKINS
  Standpipe Hydro   11/12/2015   Partial Approval   TODD JENKINS
  Standpipe Flush   11/16/2015   Approved   TODD JENKINS
  Standpipe Hydro   11/16/2015   Approved   TODD JENKINS
  Rough   11/17/2015   Partial Inspection   TODD JENKINS
  Special/Order Compliance   11/17/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   11/23/2015   Partial Approval   TODD JENKINS
  Rough   11/23/2015   Partial Approval   TODD JENKINS
  Rough   12/02/2015   Partial Approval   TODD JENKINS
  Overhead Hydro   12/07/2015   Partial Approval   TODD JENKINS
  Rough   12/07/2015   Corrections Issued   TODD JENKINS
  Standpipe Hydro   12/07/2015   Not Ready for Inspection   TODD JENKINS
  Rough   12/09/2015   Not Ready for Inspection   TODD JENKINS
  Rough   12/09/2015   Partial Approval   TODD JENKINS
  Rough   12/10/2015   Partial Approval   TODD JENKINS
  Rough   12/18/2015   Partial Approval   TODD JENKINS
  Fire Pump Hydro   12/23/2015   Partial Approval   TODD JENKINS
  Rough   12/23/2015   Partial Approval   TODD JENKINS
  Final   01/14/2016   Corrections Issued   TODD JENKINS
  Final   01/19/2016   Corrections Issued   VICENTE DIAZ
  Special/Order Compliance   01/20/2016   Partial Approval   TODD JENKINS
  Final   01/27/2016   Partial Approval   TODD JENKINS
  Final   02/01/2016   Partial Approval   TODD JENKINS
  Final   02/03/2016   Not Ready for Inspection   TODD JENKINS
  Special/Order Compliance   02/03/2016   Partial Inspection   TODD JENKINS
  Fire Pump Test   02/04/2016   Approved   STEVEN KIMBLE
  Fire Pump Test   02/04/2016   Approved   TODD JENKINS
  Final   02/06/2016   Partial Approval   TODD JENKINS
  Fire Dept Connection Flush   02/06/2016   Approved   TODD JENKINS
  Final   02/08/2016   Not Ready for Inspection   TODD JENKINS
  Final   02/18/2016   Partial Approval   TODD JENKINS
  Final   03/11/2016   Partial Approval   TODD JENKINS
  Final   03/14/2016   Partial Inspection   TODD JENKINS
  Final   03/16/2016   Partial Approval   TODD JENKINS
  Final   03/21/2016   Partial Inspection   TODD JENKINS
  Final   03/24/2016   Partial Approval   TODD JENKINS
  Final   04/05/2016   Partial Inspection   TODD JENKINS
  Final   04/07/2016   Partial Approval   TODD JENKINS
  Final   04/19/2016   Partial Approval   TODD JENKINS
  Final   04/25/2016   Partial Approval   TODD JENKINS
  Final   05/03/2016   Partial Approval   TODD JENKINS
  Final   05/09/2016   Partial Approval   TODD JENKINS
  Final   05/13/2016   Partial Approval   TODD JENKINS
  Final   06/13/2016   Permit Finaled   TODD JENKINS